Construction, Commissioning & Start-up of Electrical, Instrument & Control System for Sirjan Air Separation Plant

Time frame: 6 Month

Installation, test, pre-commissioning of electrical, instrument, control and telecommunication system is in SBS co. scope of work.
Main equipment’s are as followings :
-Power transformer
-MV switchgear
-LV switchgear
-VFD of main air compressor,9.4MW
-Diesel Generator
-Power & control cable about 25 km
-AC UPS & DC Charger
-Capacitor Bank
-Earthing system
-Lighting system
-Support about 20 ton
-Tray & ladder about 2000m
-Telephone, paging, CCTV
-F&G system
-Control cable about 15km
-Instrument devices
-Tubing abou
-Valves